Harmonised product standards include Annex ZA, which sets out all the minimum requirements for demonstrating compliance with the relevant standard, namely the Initial Type Testing (ITT) to be carried out and the applicable Assessment and Verification of Constancy of Performance (AVCP) system(s) established for that specific product and its intended use.
The respective responsibilities for carrying out the above-mentioned ITT and FPC (Factory Production Control) activities are therefore clearly defined.
The systems for attestation of conformity provided for under the Construction Products Directive are:
| AVCP | Manufacturer responsibilities | Notified Body responsibilities | Documents for CE marking |
| 4 | Initial type testing of the product Factory Production Control | Declaration of Performance issued by the manufacturer | |
| 3 | Factory Production Control | Initial type testing of the product | Declaration of Performance issued by the manufacturer |
| 2+ | Initial type testing of the product Factory Production Control Testing of samples in accordance with a predetermined test plan | Certification of Factory Production Control based on: 1. initial inspection; 2. continuous surveillance, assessment and approval of Factory Production Control. | Declaration of Performance issued by the manufacturer + Certificate of conformity of Factory Production Control (FPC) |
| 1 | Factory Production Control Further testing of samples in accordance with a predetermined test plan | Certification of the constancy of performance of the product based on: 1. initial type testing of the product; 2. initial inspection of the manufacturing plant and Factory Production Control; 3. continuous surveillance, assessment and approval of Factory Production Control. | Declaration of Performance issued by the manufacturer + Certificate of constancy of performance of the product |
| 1+ | Factory Production Control Further testing of samples in accordance with a predetermined test plan | Certification of the constancy of performance of the product based on: 1. initial type testing of the product; 2. initial inspection of the manufacturing plant and Factory Production Control; 3. continuous surveillance, assessment and approval of Factory Production Control; 4. testing of samples taken at the manufacturing plant, on the market or on the construction site | Declaration of Performance issued by the manufacturer + Certificate of constancy of performance of the product |